The brief.

Delivered asDilapidations, Roofing, Electrical, JCT Contract

We were invited to tender for this project and were subsequently awarded it. The works were carried out on behalf of the landlord and administered by a Contract Administrator under a JCT contract, so every instruction, valuation and variation went through a formal process rather than a conversation on site.

The building is a typical mid-terrace market town shop with a large flat-roofed extension added to the rear. Our remit was to strip out the previous tenant's fixtures and fittings, carry out the remedial work needed to make the unit weather tight, and create a clean blank canvas ready for a prospective new tenant. Externally that meant scaffolding, stripping and re-roofing both front and rear elevations, reducing the height of the chimney stack and repointing and capping it, repointing the front facade stonework, and re-felting the large flat roof to the rear. Internally, a new fire escape door, second fix joinery, full redecoration, an EICR electrical test with the mains board updated as a result, and new floor coverings throughout.

The interesting part was not the construction, it was the logistics. A Market Place address in a busy North Yorkshire town means every skip, every scaffold lift and every waste run has to be planned around the public and around neighbouring businesses that are still trading. That planning is the difference between a job that finishes on time and one that becomes everybody's problem.

Scope of works.

Every trade below was delivered by us or by a company in the group, under one contract and one point of contact.

  1. 01 Scaffolding installed to allow safe working at height
  2. 02 Front and rear roofs stripped and re-roofed
  3. 03 Chimney stack reduced in height, repointed and capped off
  4. 04 Front facade stonework repointed
  5. 05 Guttering cleaned out and replaced where required
  6. 06 Large rear flat roof cleaned off, plywooded and re-felted
  7. 07 Overgrown vegetation cleared and weed killed to the rear
  8. 08 Shop front and windows redecorated, glazing cleaned
  9. 09 All previous tenant contents and fit-out removed and disposed of
  10. 10 New fire escape door installed
  11. 11 EICR electrical test carried out and mains board updated
  12. 12 First floor offices re-carpeted and WC vinyl laid

The difference.

Same building, same angle. Click any photograph to open it full size.

Before
After

Before

5

In progress

6

Completed

5

What this project proves.

Capabilities demonstrated on this job. Follow any of them for how we approach that work and where else we have done it.

Have a project like this?

Send us the brief, a drawing or just the postcode. Free site survey across the North and the Midlands, fixed written quote within the week.

Part of The AB Group

One family. A group of companies.

Call us