Overview of Works

Circa 95sqm of Paving to patio areas.

Works in brief:

  • Take up existing flags and remove off site
  • Improve subbase and compact
  • Supply and install new paving, carefully cutting around manholes and allowing a 150mm gravel boarder to all perimeter areas
  • Re clad steps to garden area.
  • Seal new paving and resin joints.
  • Manually mortar point step riser areas.
  • Supply and install 20mm pea gravel boarder.

Duration of works 2 Weeks

Project Location

Linton, Wetherby

Project Status

April 12, 2018

Completed Date

95 sqm